The Scheduled Jobs Not Run report displays all jobs scheduled by CA WA CA 7 Edition that did not run and the reasons for job failures.
SASSHR01 CA-7 SCHEDULED JOBS NOT RUN 03/14/yy 11:07 PAGE 1 ----------------------------------------------------------------------------------------------------------------------------------- JOB CA-7 SCHD MAIN REQUIREMENTS DUE-OUT DEAD-LINE SUBMIT FLAGS COMMENTS NAME NO ID ID E I EN IN MC DATE TIME DATE TIME DATE TIME ----------------------------------------------------------------------------------------------------------------------------------- PKFIS587 0678 103 SY0 00 01 00 00 01 02/01/yy 11:32 02/01/yy 11:17 02/01/yy 11:12 18 08 00 01 10 10 40 CANCEL REQ PPDTC500 0739 002 SY0 00 01 00 01 01 02/01/yy 20:00 02/01/yy 19:51 00 08 00 01 00 00 00 CANCEL REQ PPMGK711 0647 001 SY0 03 04 00 01 01 02/01/yy 11:20 02/01/yy 11:09 02/01/yy 10:45 10 48 00 01 00 00 00 CANCEL REQ PPPTR901 0000 001 SY0 00 00 00 00 00 02/01/yy 14:00 02/01/yy 13:53 02/01/yy 12:00 00 00 08 00 00 10 00 NXT CY OFF
SASSHR01 CA-7 SCHEDULED JOBS NOT RUN 03/14/yy 11:07 PAGE 2 ----------------------------------------------------------------------------------------------------------------------------------- JOB CA-7 SCHD MAIN REQUIREMENTS DUE-OUT DEAD-LINE SUBMIT FLAGS COMMENTS NAME NO ID ID E I EN IN MC DATE TIME DATE TIME DATE TIME ----------------------------------------------------------------------------------------------------------------------------------- *** T O T A L S *** 00004 JOBS NOT RUN. 0000:42 WORK ON HAND. 0000298 JOBS RUN. 001.34 PERCENTAGE NOT RUN. *** E N D O F R E P O R T ***
This report contains the following fields:
Identifies the CA WA CA 7 Edition job name.
Identifies the CA WA CA 7 Edition job number.
Identifies the CA WA CA 7 Edition schedule ID.
Identifies the CA WA CA 7 Edition system ID. For XPJOBs, this value is always XPJ. For agent jobs, this value is the agent job type.
Specifies the status of the job requirements subdivided as follows:
Specifies the external requirements satisfied.
Specifies the internal requirements satisfied.
Specifies the external requirements not satisfied.
Specifies the internal requirements not satisfied.
Specifies the master requirements count.
Identifies the date and time by which the job must be complete.
Identifies the date and time by which the job must start.
Identifies the date and time the job was submitted.
Identifies the job status flags from the JQREC control block. See fields JQFLG1, JQFLG2, and JQJFLG1 through JQJFLG5 (in that order) in the JQREC macro for details on the flag bytes.
Provides comments explaining why the job did not run, according to the following:
Indicates the job did not meet the DONT SCHEDULE BEFORE/AFTER CRITERIA.
Indicates the job was scheduled but canceled in the xxx queue.
Indicates the job was scheduled, but disaster recovery mode was active and the job's disaster recovery class was not active.
Indicates the job was triggered, but disaster recovery mode was active and the job's disaster recovery class was not active.
Indicates the job was considered to have already run earlier. This situation can occur when the SSCAN command is used, and the PERSTART command is used to set the time backwards.
Indicates the job schedule was locked.
Indicates the job set off for next cycle.
Indicates a CA WA CA 7 Edition queue error occurred. Examine the log data for a more detailed error message at the time the job was set for scheduling.
Indicates the job is set to skip the next cycle.
Specifies the total number of jobs that were not run for some reason.
Specifies the forecasted elapsed time required to complete the jobs that have not yet executed as of the end of the reporting period.
Specifies the total number of jobs that were run during this reporting period.
Specifies the percentage of total jobs that were not run. Calculated as JOBS NOT RUN divided by JOBS RUN count.
|
Copyright © 2015 CA Technologies.
All rights reserved.
|
|