The Expanded IDs Usage report lists each type of object (job, schedule, triggers, and so on) in a separate section of the report. Each section begins with a header line that explains what is contained in that section. The report includes a section only when objects of that type contain IDs greater than 255. For example, the report does not include the Schedules section when none of the schedules have a schedule ID greater than 255.
The report can display the following sections:
|
Section Header |
Action to Take |
|---|---|
|
ARF Queue |
This temporary situation is resolved as CA WA CA 7 Edition Version 12.0 continues execution. |
|
Active ARFSETs, Active ARFSET Conditions, Active ARFSET Actions |
Let all jobs using the ARFSET complete successfully. |
|
Active CPM Flows |
Let the job stream to complete successfully or use the FLOWD command. |
|
Active Networks |
Let the networks complete by using the LOGIN and LOGOUT commands, or use the Queue Maintenance Cancel command. |
|
Active Virtual Resources |
Let the job complete successfully, or use the CANCEL command, or use the PRSCF command |
|
Active Workload |
Let the job complete successfully or use the CANCEL command. |
|
ARFSET Definitions, ARFSET Conditions, ARFSET Actions |
Use AR.3 to update the ARFSET. |
|
Global Variables |
Use the /GVAR command to update the global variable. |
|
Job Definition |
Use DB.1 to update the job definition. |
|
Manual Virtual Resources |
Use the PRSCF command. |
|
Prior-Run Queue |
Use the PRRNDEL command. |
|
Requirements |
Use DB.3.x to update the requirement. |
|
Run Log |
The reversion utility updates or deletes this record. |
|
Schedules |
Use DB.2.1, DB.2.2, or DB.2.3 to update the schedule definition. |
|
Triggers |
Use DB.2.4, DB.2.5, or DB.2.6 to update the trigger definition. |
|
Virtual Resources |
Use RM.1 to update the virtual resource and job relationship. |
|
Copyright © 2015 CA Technologies.
All rights reserved.
|
|