Consider scheduling jobs that run around the midnight boundary on different calendars that as a rule have Tuesday through Saturday as available processing days. This setup results from day designation changes from 24:00 to 00:01 (Sunday turns to Monday, and so on).
On the DB.2.1-E panel, jobs are scheduled with a DOTM (due out time). The DOTM is for the day that the job is to complete.
The job enters the queue late Sunday through Thursday.
Schedule that job on Tuesday through Saturday because those days are the days of the week on which the job is due to complete.
Business Value:
This best practice results in third shift work schedules correctly.
|