Changes to Existing Features › CPM Flow Corequisite Resources Changes
CPM Flow Corequisite Resources Changes
Two elements of the resource name defining a CPM FLOW support new formats:
- The SCHID of the ending job of a critical path can now be set to 0 (zero). This automatically sets the ending job SCHID to match the starting job. Setting the ending SCHID to 0 permits the same FLOW resource name to be used for the same job flow executing under different SCHIDs instead of defining separate FLOW resource names for each single SCHID.
- The end time of the ending job specified to support Service Level Agreements can now be relative to the FLOW starting time. Adding a + (plus) before the endtarget element, +hhmm, indicates the last job is expected to end before the FLOW starting time plus the hhmm value.
Note: For more information, see the Database Maintenance Guide and the Interface Reference Guide.