Previous Topic: CPM1045INext Topic: CPM1070E


CPM1050I

Flow Display:

CPM1051I

Flow=('flowid')

CPM1052I

LoadTime='ltim' SlaTime='slatim'

CPM1053I

StartTime='stim' ETA='etim'

CPM1054I

FirstJob='fjob' LastJob='ljob'

CPM1055I

LastEvenTime='evtim' LastEventJob='lejob'

CPM1056I

JobCount='jct' Completed='cct'

CPM1057I

PathCount='pct' CriticalPath='cpid'

CPM1058I

Status='fstat' LastCalc='ctim'

CPM1059I

JobPct='jpct' EtaPct='epct'

CPM1060I

LastEventType='evt' Abended='abcnt'

CPM1061I

Job='jnam'

CPM1062I

SLAtime='jsla' EndTime='jetim'

CPM1063I

EarlyStart='jest' ActualStart='jast'

CPM1064I

HistRuntime='hrtim' ActualRuntime='artim'

CPM1065I

Successors='sct' Predecessors=('prct','cpct')

CPM1066I

Status='jstat'

Reason:

This message is the response to a DISPLAY FLOW command. Messages CPM1061I through CPM1066I appear only if a selective form of the command was issued. These messages are repeated for each job in the work flow.

abcnt

Indicates the number of jobs that are currently in ABEND status.

artim

Indicates the actual elapsed time for the job.

cct

Indicates the number of completed jobs.

cpct

Indicates the number of completed predecessor jobs.

cpid

Indicates the ID of the current critical path.

ctim

Indicates the time of day when last CA CPM calculation was performed for the flow.

epct

Indicates the estimated percentage complete, based on current ETA.

etim

Indicates the estimated time the flow is to complete.

evt

Indicates the name of the most recent flow event.

evtim

Indicates the time of day the last event for the flow that CA CPM received.

fjob

Indicates the name of the first job in the flow.

fstat

Indicates the status of the flow.

hrtim

Indicates the historical runtime for the job.

jast

Indicates the time of day when the job actually started.

jct

Indicates the total number of jobs in the flow.

jest

Indicates the time of day before which the job should not start.

jetim

Indicates the time of day when the job completed.

jnam

Indicates the name of the job.

jpct

Indicates the percentage of jobs that have completed.

jsla

Indicates the time of day by which the job must be completed to be considered on time.

jstat

Indicates the status of the job.

lejob

Indicates the name of the last job for which an event that CA CPM received.

ljob

Indicates the name of the last job in the flow.

ltim

Indicates the time of day when the flow was loaded into the CA CPM environment.

pct

Indicates the number of distinct paths in the flow.

prct

Indicates the number of predecessor jobs.

sct

Indicates the number of successor jobs.

slatim

Indicates the time of day by which the flow must complete to be considered on time.

stim

Indicates the time of day when the first job start event for the flow that CA CPM received.

Action:

None.