Reason:
This message is the response to a DISPLAY FLOW command. Messages CPM1061I through CPM1066I appear only if a selective form of the command was issued. These messages are repeated for each job in the work flow.
Indicates the number of jobs that are currently in ABEND status.
Indicates the actual elapsed time for the job.
Indicates the number of completed jobs.
Indicates the number of completed predecessor jobs.
Indicates the ID of the current critical path.
Indicates the time of day when last CA CPM calculation was performed for the flow.
Indicates the estimated percentage complete, based on current ETA.
Indicates the estimated time the flow is to complete.
Indicates the name of the most recent flow event.
Indicates the time of day the last event for the flow that CA CPM received.
Indicates the name of the first job in the flow.
Indicates the status of the flow.
Indicates the historical runtime for the job.
Indicates the time of day when the job actually started.
Indicates the total number of jobs in the flow.
Indicates the time of day before which the job should not start.
Indicates the time of day when the job completed.
Indicates the name of the job.
Indicates the percentage of jobs that have completed.
Indicates the time of day by which the job must be completed to be considered on time.
Indicates the status of the job.
Indicates the name of the last job for which an event that CA CPM received.
Indicates the name of the last job in the flow.
Indicates the time of day when the flow was loaded into the CA CPM environment.
Indicates the number of distinct paths in the flow.
Indicates the number of predecessor jobs.
Indicates the number of successor jobs.
Indicates the time of day by which the flow must complete to be considered on time.
Indicates the time of day when the first job start event for the flow that CA CPM received.