Flow Detail

Type an S next to a Flow Name in the Flow Display to display the Flow Detail screen.

--------------------- CA-CRITICAL PATH MONITOR FLOW DETAIL-------------------- COMMAND ===> Flow Name: BDJFLOW4 Product: 7 Status: Complete-Late First Job: JFLOW001 (004) Last Job: JFLOW010 (004) Number Of: Paths . . . . . . 1 Critical Path # . . . 1 Jobs . . . . . . 2 Completed Jobs . . 2 Abended Jobs . . . 0 Times: Percents: Load . . . . . . . 2009-07-30 10:56 Jobs Complete . . .100 % Last Calculation . 2009-07-30 10:56 Time Complete . . .100 % SLA . . . . . . . 2009-07-29 16:00 ETA . . . . . . . 2009-07-30 10:56 Last Event: Event for Job . . JFLOW010 (004) Time of Event . . 2009-07-30 10:56 Type . .CMPL Press Enter to refresh, or enter END to exit.

Refresh this screen by pressing Enter.

This panel contains the following fields:

Flow Name

Indicates the name of the flow being displayed.

Product

Indicates the type of job management product. Possible values are the following:

Status

Indicates the status of the flow. See the list of possible statuses in the Flow Display section in this chapter.

First Job

Indicates the first job in the flow. The job name in the example shown here is in CA Workload Automation SE format.

Last Job

Indicates the last job in the flow. The job name in the example shown here is in CA Workload Automation SE format.

Number of Paths

Indicates the total number of job successor routes that can be taken from the first job in the flow to the last job.

Number of Jobs

Indicates the total number of jobs in the flow. Not all these jobs may be on the critical path.

Number of Completed Jobs

Indicates the total number of jobs in the flow that have completed successfully.

Number of Abended Jobs

Indicates the total number of jobs in the flow that are currently in an abended or failed status.

Critical Path #

Indicates the specific path that CA CPM has calculated to have the longest execution time.

Load Time

Indicates the date and time when CA CPM learned about the flow.

Last Calculation Time

Indicates the date and time when CA CPM last evaluated the flow to determine whether it can complete by the SLA.

SLA Time

Indicates the date and time, defined by the job management product, when the flow must complete.

ETA Time

Indicates the date and time calculated by CA CPM that the flow is expected to complete. If the flow has completed, this field shows the actual end time.

Jobs Complete Percent

Indicates the percentage of the jobs in the flow that have successfully completed.

Time Complete Percent

Indicates the percentage of the total execution time that has elapsed.

Last Event

Displays the job, date and time, and type of the most recent event that CA CPM has received for this flow. The job name in the example shown here is in CA Workload Automation SE format. The following are possible values for the Event Type:

LOAD

Indicates the flow has been loaded, but the first job has not yet started.

STRT

Indicates the job has started.

CMPL

Indicates the job has successfully completed.

ABTM

Indicates the job has abended or failed.

DELT

Indicates the job has been canceled on CA Workload Automation SE.

PURG

Indicates the job has been force completed on CA Workload Automation SE.

More information:

Job Names