Type an S next to a Flow Name in the Flow Display to display the Flow Detail screen.
--------------------- CA-CRITICAL PATH MONITOR FLOW DETAIL-------------------- COMMAND ===> Flow Name: BDJFLOW4 Product: 7 Status: Complete-Late First Job: JFLOW001 (004) Last Job: JFLOW010 (004) Number Of: Paths . . . . . . 1 Critical Path # . . . 1 Jobs . . . . . . 2 Completed Jobs . . 2 Abended Jobs . . . 0 Times: Percents: Load . . . . . . . 2009-07-30 10:56 Jobs Complete . . .100 % Last Calculation . 2009-07-30 10:56 Time Complete . . .100 % SLA . . . . . . . 2009-07-29 16:00 ETA . . . . . . . 2009-07-30 10:56 Last Event: Event for Job . . JFLOW010 (004) Time of Event . . 2009-07-30 10:56 Type . .CMPL Press Enter to refresh, or enter END to exit.
Refresh this screen by pressing Enter.
This panel contains the following fields:
Indicates the name of the flow being displayed.
Indicates the type of job management product. Possible values are the following:
Indicates the status of the flow. See the list of possible statuses in the Flow Display section in this chapter.
Indicates the first job in the flow. The job name in the example shown here is in CA Workload Automation SE format.
Indicates the last job in the flow. The job name in the example shown here is in CA Workload Automation SE format.
Indicates the total number of job successor routes that can be taken from the first job in the flow to the last job.
Indicates the total number of jobs in the flow. Not all these jobs may be on the critical path.
Indicates the total number of jobs in the flow that have completed successfully.
Indicates the total number of jobs in the flow that are currently in an abended or failed status.
Indicates the specific path that CA CPM has calculated to have the longest execution time.
Indicates the date and time when CA CPM learned about the flow.
Indicates the date and time when CA CPM last evaluated the flow to determine whether it can complete by the SLA.
Indicates the date and time, defined by the job management product, when the flow must complete.
Indicates the date and time calculated by CA CPM that the flow is expected to complete. If the flow has completed, this field shows the actual end time.
Indicates the percentage of the jobs in the flow that have successfully completed.
Indicates the percentage of the total execution time that has elapsed.
Displays the job, date and time, and type of the most recent event that CA CPM has received for this flow. The job name in the example shown here is in CA Workload Automation SE format. The following are possible values for the Event Type:
Indicates the flow has been loaded, but the first job has not yet started.
Indicates the job has started.
Indicates the job has successfully completed.
Indicates the job has abended or failed.
Indicates the job has been canceled on CA Workload Automation SE.
Indicates the job has been force completed on CA Workload Automation SE.
|