You have many options for scheduling a migration. This list presents possible scheduling needs and the parameters to implement them:
- Each night, by the CA View standard backup cycle
DSK2MIGD=BBBBBBB
DAYS=YYYYYYY
The DAYS initialization parameter determines which days of the week the CA View backup cycle is to run.
- Automatically, by the migration subtask, Monday through Friday only. Every 45 minutes from 9 p.m. to 11 p.m., and every 45 minutes from 1 a.m. to 5 a.m.
DSK2MIGD=AAAAANN
DSK2INTV=0045
DSK2TIME=2100-2300,0100-0500
- When the system administrator manually invokes the migration subtask (no automatic migration)
DSK2MIGD=MMMMMMM