Although we do not advise overriding retention criteria once it has been defined, it is possible to shorten or extend retention periods that have been defined using the following retention methods:
If a number of days has been specified in the count field of the retention statement, changing KEEPDT will not help because the keep date is automatically recalculated each time TRS runs. The only way to shorten or extend the retention period is to manually change the creation date (CDATE) field (see discussion below). Changing the date from which the keep date is calculated will also change the keep date.
The following two methods may be used although we do not recommend changing the creation date. This can cause serious problems for cycle-controlled data sets. It also destroys any chronological information which could be used for tracing possible problems.
|
Copyright © 2014 CA.
All rights reserved.
|
|