The region uses the relationships between resources during automated system startup and shutdown to determine the order in which to start or stop resources.
There are two parties to a relationship: parent and child.
During automated operation, a parent must be active before dependent resources (its children) may be started. For example, JES must be active before CICS may be started.
Similarly, a parent cannot be stopped automatically unless all its children are inactive.