If you want certain time periods included and others not included on the graph, you can use a combination of the schedule and dates features. The /SCHEDULE qualifier, and the schedule time clocks in the window interface, allow you to specify desired hours on a weekly basis for inclusion on the graph. If you need more specific selection time frames, you can use a DATES file (see the /DATES qualifier), which specifies an unlimited number of date ranges, to indicate the desired time frames for inclusion in the graph.
You may want to use both the /DATES qualifier and the /SCHEDULE qualifier together. For example, if you need a graph depicting an average Monday through Thursday prime time for the first week of September, October, November and December of 2005, your schedule and dates file would be as follows:
MYDATES.DAT: 07-SEP-2005,11-SEP-2005 05-OCT-2005,09-OCT-2005 02-NOV-2005,06-NOV-2005 07-DEC-2005,11-DEC-2005
To use this dates file
$ ADVISE PERFORMANCE GRAPH/SCHEDULE=(NOWEEKENDS,WEEKDAYS=(9-12 -,
_$ 14-17),NOFRIDAY)/DATES=MYDATES.DAT/AVERAGE=WEEKLY
|
Copyright © 2008 CA.
All rights reserved.
|
|