User Preparation and Planning

Use the following steps to prepare and plan:

  1. Review the results of the Phase Two implementation.
  2. Determine the groups to be used in your CA‑PanAPT system.
  3. Plan CA‑PanAPT security and update Activity records to reflect your needs.
  4. Review your Production files and the establish order of implementation for each set of libraries.
  5. Establish protocol and schedule of the utilization of CA‑PanAPT in accordance with your current needs or procedures.
  6. Document your CA‑PanAPT procedures as you would any other data center procedure.
  7. Schedule your internal training for other users of CA‑PanAPT to demonstrate the system, and to alert them to new procedures.