OPSVIEW Control Option › How to Delete a Node and Its Subnodes › The Effect of the Action Verification Setting
The Effect of the Action Verification Setting
The setting of the Action Verification field on the OPSVIEW General Settings panel (option 0.1) affects the outcome of the D line command:
- If the Action Verification field is set to Y, CA OPS/MVS requests confirmation before it deletes the node and its subnodes. For details, see Confirming the Deletion in this chapter.
- If the Action Verification field is set to N, CA OPS/MVS deletes the node without requesting confirmation. For details, see Deleting a Node and Its Subnodes Without Confirmation in this chapter.
For details about the OPSVIEW General Settings panel and the Action Verification field, see How to Modify OPSVIEW Options (Option 0.1) in the chapter “Using the OPSVIEW Parameters Option.”