3. REPORTS › 3.2 Standard Analysis Reports › 3.2.1 System Reliability Summary Report
3.2.1 System Reliability Summary Report
The System Reliability Summary Report provides an overview of
the key errors and events that have occurred for the
processor and associated storage and channels and the
software, hardware devices, and the magnetic media. Counts
of the number of failures and other significant events are
provided by unique system identifier.
See Section 3.1.1 for more information on this report.
REPORT FORMAT:
See Section 3.1.1 for an example of the output generated by
the System Reliability Summary Report.
DATA SOURCE (file/time-span):
SRLDRL, SRLMRL, SRLTRL, SRLXRL and SRLRNC at the
DETAIL time-span.
DATA ELEMENTS USED:
The data elements used for this report are:
___________________________________________________________
| | |
| FILE | DATA ELEMENTS |
|__________|_______________________________________________|
| | |
| SRLDRL | DRLPRMCT DRLTMPCT |
| SRLMRL | MRLLOGTY MRLPRMCT MRLTMPCT MRLMTS |
| SRLTRL | TRLPRMCT |
| SRLXRL | XRLPRMCT |
| SRLRNC | RNCTYPE |
| | |
|__________________________________________________________|
REPORT DEFAULTS AND CONSIDERATIONS
The following table summarizes the keywords which may be used
for the System Reliability Summary Report and gives their
default values.
A complete list of keywords and their descriptions can be
found in Section 3.2.9.
KEYWORD DEFAULT
--------------- --------------------
CURRENT enddate yesterday's date
TIMESPAN DETAIL DETAIL
CYCLES nn DAYRANGE+1
DAYRANGE n 7
SYSID list all SYSIDs
CPUSER list all CPUSERs
EXCLUDE YES EXCLUDE NO
REPORT RELSM -
----------------------------------------
Notes:
1. Only the enddate is used from the CURRENT parameter.
If a startdate is specified, it is ignored.
2. The only valid TIMESPAN value is DETAIL. The
Reliability Incident file is used and it is only
maintained in the DETAIL timespan.
3. CYCLES may have any value, however, data will only be
used from the dates contained in the period
enddate-DAYRANGE+1 to enddate
4. The maximum DAYRANGE value is 7 days.
5. CPUSER may be used to limit data selected. It does
not appear on the report.
6. If other keywords are used, they MAY AFFECT the
report. They are NOT ignored by the report.