2. PERFORMANCE REPORTING ANALYSIS › 2.8 Sysplex Analysis › 2.8.3 Standard Output › 2.8.3.6 Coupling Facility Configuration
2.8.3.6 Coupling Facility Configuration
The Coupling Facility Configuration report tracks the
coupling facility activity in terms of utilization, structure
configuration and request activity. A sample report is
shown in Figure 2-214.
REPORT OPTIONS
The Coupling Facility Configuration report supports standard
time selection options, SYSID and/or XCF System selection,
and specific XCF Structure selection. These selection
options are discussed in Sections 2.8.5 and 2.8.5.5.
DATA ELEMENTS
The elements reported are divided into three categories:
o CF CPU Activity
o CF Configuration
o CF Request Activity
CF CPU ACTIVITY
The CPU Activity elements describe the utilization of
processing power on the coupling facility itself. These
measures are repeated for each structure that was selected
for reporting.
AVG The average number of processors on this
PROCESSORS: Coupling Facility during the time period shown:
CFPAVCPU.
AVG % The average percent busy for the processors on
PROCESSOR this Coupling Facility during the time period
BUSY: shown: CFPPCBSY.
AVG % The average percent wait time for the
PROCESSOR processors on the Coupling Facility during the
WAIT: time period shown: CFPPCWAT.
PERCENT CF The percentage of intervals (RMF recording
CONNECTED: intervals) during which the Coupling Facility
was connected to the reporting system at the
end of them measurement interval: CFPPCCON
MAX % The maximum percent busy for the processors on
PROCESSOR the Coupling Facility during the time period
BUSY: shown: CFPMXPCB
MAX % The maximum percent wait time for the
PROCESSOR processors on the Coupling Facility during the
WAIT: time period shown: CFPMXPCB
CF CONFIGURATION
These elements display storage available and allocated
information for the coupling facility and reported structure.
These items should be relatively static over the duration of
the analysis unless some sort of reconfiguration activity has
occurred.
AVG STORAGE The average amount of storage defined on the
DEFINED: coupling facility. This includes both control
and non-control storage: CFPAVTSD.
AVG STORAGE The average amount of free storage on the
FREE: Coupling Facility during the time period shown.
This includes both control and non-control
storage: CFPAVTSF.
AVG CNTL The average amount of control storage defined
STG DEFINED: on the Coupling Facility during the time period
shown. The difference between this value and
the average storage defined represents the
average non-control storage: CFPAVTSD.
AVG CNTL The average amount of free control storage on
STG FREE: the Coupling Facility during the time period
shown: CFPAVCSF.
AVG The average size of the reported structure
STRUCTURE during the time period shown: CFSAVSIZ.
SIZE:
CF REQUEST ACTIVITY
The elements reported in this section reflect the request
activity associated with the specific structure defined to
the coupling facility and being reported on in the analysis.
% STRUCTURE The percentage of intervals (RMF recording
CONNECT: intervals) during the reported time period, in
which the structure was connected to the system
at the end of the interval: CFRPCCON
ASYNC The average number of asynchronous requests per
REQS/SEC: second during the reported time period from the
reporting system using the Coupling Facility
structure: CFRPSARC.
SYNCH The average number of synchronous requests per
REQS/SEC: second during the reported time period from the
reporting system using the Coupling Facility
structure: CFRPSSRC.
QUEUED The average number of queued requests per
REQS/SEC: second during the reported time period from the
reporting system using the Coupling Facility
structure: CFRPSQRC.
REQS/SEC The average number of requests completed per
COMPLETED: second during the reported time period
originating on the reporting system: CFRPSRQC.
DUMP DELAYED The average number of request per second that
REQS/SEC: were delayed due to dump serialization
activity on the Coupling Facility: CFRPSDRC.
AVG SVC The average service time for handling the
TIME ASYNCH: asynchronous request activity from the
reporting system using this Coupling Facility
structure: CFRAVATM.
AVG SVC The average service time for handling the
TIME SYNCH: synchronous request activity from the reporting
system using this Coupling Facility structure:
CFRAVSTM.
AVG SVC The average service time for handling the
TIME QUEUED: queued request activity from the reporting
system using this Coupling Facility structure:
CFRAVQTM.
DUMP SER The average number of Coupling Facility
DELAY RATE: requests per second, that were delayed because
dump serialization was in process during the
time period shown: CFRPSDUQ
HI PRI The average number of Coupling Facility high
REQ RATE: priority requests that were queued, per second,
during the time period shown: CFRPSHPQ
LO PRI The average number of Coupling Facility low
REQ RATE: priority requests that were queued, per second,
during the time period shown: CFRPSLPQ
CA MICS Performance Manager
HOURLY COUPLING FACILITY CONFIGURATION
SYSTEM = S072 CF SYSTEM = S072 RUNDATE = Feb 2, yyyy
COUPLING FACILITY NAME = COUPLER CF STRUCTURE= IXCXCFL
----------------------------------------------------------------------------
| |
| HOUR-DATE (HR-MM/DD): 14-08/yy 15-08/yy 16-08/yy 17-08/yy CHANGE % |
| |
|--------------------------------------------------------------------------|
| |
| CF CPU ACTIVITY |
| --------------- |
| |
| AVG PROCESSORS 2.00 2.00 2.00 2.00 --- |
| AVG % PROCESSOR BUSY 28.11 % 28.79 % 28.47 % 28.42 % 1.10 % |
| AVG % PROCESSOR WAIT 71.87 % 71.19 % 71.52 % 71.56 % -0.43 % |
| PERCENT CF CONNECTED 100.0 % 100.0 % 100.0 % 100.0 % --- |
| MAX % PROCESSOR BUSY 28.11 % 28.84 % 28.48 % 28.42 % 1.10 % |
| MAX % PROCESSOR WAIT 71.87 % 71.25 % 71.53 % 71.56 % -0.43 % |
| |
|--------------------------------------------------------------------------|
| |
| CF CONFIGURATION |
| ---------------- |
| |
| AVG STORAGE DEFINED 240M 240M 240M 240M --- |
| AVG STORAGE FREE 218M 218M 218M 218M --- |
| AVG CNTL STG DEFINED 240M 240M 240M 240M --- |
| AVG CNTL STG FREE 218M 218M 218M 218M --- |
| AVG STRUCTURE SIZE 6308K 6308K 6308K 6308K --- |
| |
|--------------------------------------------------------------------------|
| |
| CF REQUEST ACTIVITY |
| ------------------- |
| |
| % STRUCTURE CONNECT 100.0 % 100.0 % 100.0 % 100.0 % --- |
| ASYNCH REQS/SEC 62.058 61.683 61.177 61.296 -1.22 % |
| SYNCH REQS/SEC 0.000 0.000 0.000 0.000 N/A |
| QUEUED REQS/SEC 0.279 0.220 0.222 0.229 -17.92 % |
| REQS/SEC COMPLETED 62.058 61.683 61.177 61.296 -1.22 % |
| DUMP DELAYED REQ/SEC 0.000 0.000 0.000 0.000 N/A |
| AVG SVC TIME ASYNCH 0.007 0.007 0.007 0.007 --- |
| AVG SVC TIME SYNCH 0.000 0.000 0.000 0.000 N/A |
| AVG SVC TIME QUEUED 0.002 0.003 0.003 0.003 50.00 % |
| DUMP SER DELAY RATE 0.000 0.000 0.000 0.000 N/A |
| HI PRI REQ RATE 0.000 0.500 0.500 0.000 N/A |
| LO PRI REQ RATE 0.000 0.000 0.000 0.000 N/A |
| |
----------------------------------------------------------------------------
Figure 2-214. Sample Coupling Facility Configuration Report