Previous Topic: 3.3.2.4 Weekly VM Availability Report

Next Topic: 3.3.3 Monthly VM Reports

3.3.2.5 Weekly VM Throughput Report - Commands


This report quantifies the total VM throughput in terms of
the number of Q1 drops processed on an hourly basis for the
identified day and computing system over a week.

The management objective to be tracked for evaluating the VM
throughput rate is a measure of the number of Q1 drops
processed per hour.  Figure 3-58 illustrates the Weekly VM
Throughput Report based on a management objective of
processing less than 100,000 Q1 drops in any given hour.

The following user options apply to this report:

Weekly VM Command Rate:  The target and maximum number of Q1
drops processed per hour by VM.  The target amount is used
for a reference line on the graph and the maximum is used to
set the maximum value on the graph's vertical axis.

    &VMCWCAX and &VMCWCRF define the vertical axis maximum
         scaling and reference line for hourly Q1 drop rate
         execution in the weekly reports.

    %LET VMCWCAX = 140000;
    %LET VMCWCRF = 100000;

A full description of the user options is provided in Section
3.3.4.1, VM Report Options.

Figure 3-58 quantifies the number of Q1 drops processed with
the horizontal axis representing the hours of each day and
the vertical axis charting the Q1 drops processed.

The management objective for VM throughput is shown by the
dashed horizontal reference line printed across the chart.
In Figure 3-58, the reference line is shown at the 100,000 Q1
drops processed level of the vertical axis.  Therefore, any
hour for which the charted bar exceeds this reference line
signals that the objective to contain throughput was missed
for that hour of that day.

The vertical axis is set with a maximum value of 140,000 Q1
drops processed level to ensure uniform scaling from report
to report.  If the value is exceeded, SAS uses the highest
value encountered to set this vertical axis maximum value.


your_company_name 08:02 MONDAY, JUNE 16, 1991 4 CA MICS I/S MANAGEMENT SUPPORT SYSTEM WEEKLY VM MANAGEMENT OBJECTIVES VM THROUGHPUT (Unit: Q1 Drops/Hour) SYSTEM=VM01 BAR CHART OF COMMANDS COMMANDS 140000 + * | * | * | * | * 120000 + * | * | * | * | * 100000 +--------------------------------------*-----------------------------------------------*-------------------- | * * | * * ** | *** * ** | * *** ** * * * ** 80000 + * **** * **** * ** * * * ** *** | ** **** * **** ** ** * * * *** * **** | ******* ** ***** ** **** *** **** *** **** | ******* ** ***** ******** *** **** ******** | ********* ******** ******** *** **** ******** 60000 + ********* ********* ********** ******** ******** | ********* ********** ********** ********* ********* | ********* ********** ********** ********** ********* | ********** ********** ********** ********** ********** | ********** *********** ********** ********** ********** 40000 + *********** *********** *********** *********** ********** | *********** *********** *********** *********** ********** | *********** *********** *********** *********** ********** | *********** *********** *********** *********** ********** | *********** *********** *********** *********** *********** 20000 + *********** *********** *********** *********** *********** * * | * * *********** *********** *********** *********** *********** **** | * **** * *********** *********** *********** *********** *********** ****** | ******** *********** *********** *********** *********** *********** ******* ------------------------------------------------------------------------------------------------------------------ 111111111 111111111 111111111 111111111 111111111 111111111 111111111 89012345678 89012345678 89012345678 89012345678 89012345678 89012345678 89012345678 HOUR 10JUN91 11JUN91 12JUN91 13JUN91 14JUN91 14JUN91 15JUN91 WEEKDAY (Reference Line: 100000 Q1 Drops/Hour)


 Figure 3-58.  Weekly VM Throughput Report