Schedule Objects › About Scheduling › Schedule an Object with Events › Schedule an Object to Run Based on Events
Schedule an Object to Run Based on Events
To schedule an object to run based on events
- In the Folders management area of the CMC, select an object.
- Click Actions, Schedule.
- From the Run object list on the left of the page, select a recurrence pattern: Once, Daily, Weekly, Monthly, or by Calendar.
- Select a run option.
- Select and complete the schedule parameters for your object (scheduling option, Start Date, End Date, and so on).
- Click Events, select from the list of Available Events, and click > to add the event(s) to the list of Events to wait for.
Note: Click >> to add all the available events.
- Click the Schedule button to schedule the object.
Copyright © 2010 CA.
All rights reserved.
 
|
|