Add Elementary Processes

Follow these steps:

  1. To add the elementary processes to the GOLFER MANAGEMENT function, select the GOLFER MANAGEMENT function and then select the Add Process Add Elementary Processes icon from the Tool Bar.
  2. In the (new object) Properties dialog, enter Register Golfer, select the check box for Elementary, and click OK.
  3. If you have multiple adds still turned on, the (new object) Properties dialog remains open and you can continue to add the remaining processes. If not, select the Add Process icon again. Add the remaining elementary processes:

    If you mistyped the name of a process or forgot to select the elementary check box, double click the process to open its properties panel. If you added them all as functions (cyan) instead of processes (blue), select their parent function Golfer Management, select Edit from the Menu Bar, and select Modify to convert them all to processes.

  4. While methodologically order is not important, aesthetically it is nice to have the processes in logical sequence. To rearrange the order of the items in the diagram, click and drag them to the desired location. If you move them to an entirely different parent, the cursor switches to the change parent icon, identical to what we saw in the data model diagram.
  5. Save your model.
  6. Close the Activity Hierarchy diagram.