The following examples of using task dependencies to sequence assignments:
- During Analysis-Use the Activity Dependency Diagram to sequence Analysis assignments. For example, if Function A enables Function B, analyze the data and activities for Function A first. Failure to analyze A first require subsequent changes to B.
- During Business System Implementation (BSI)-Work first on procedures that create data in tables that other procedures reference. For example, if Procedure X creates Entity Type A and Procedure Y reads Entity Type A and creates Entity Type B, then develop Procedure X first.