The CA Endevor SCM administrator can establish a processing sequence for CA Endevor SCM Types that must be processed in a specific order. For example, COBOL copybooks must be processed before COBOL programs. This Type processing sequence can be set either at the system level (the default) or at a global level, which is referred to as Global Type Sequencing. Other Types, such as JCL, can be processed in any order. You do not need to define such Types in the Type processing sequence.
When a batch request includes multiple element Types, CA Endevor SCM first builds two request chains. One chain is composed of sequenced Types in Type sequence order, and one chain is composed of nonsequenced Types in alphabetical order. CA Endevor SCM then processes the sequenced Type chain first, as follows.
Global Type Processing is a prerequisite for the Concurrent Action Processing option. This option enables certain Types to process at the same time.
|
Copyright © 2014 CA.
All rights reserved.
|
|