Previous Topic: Control Account BaselinesNext Topic: Monitor Control Account Performance


Enter Reprogramming Adjustments for Control Accounts

During the course of executing a contract, reprogramming adjustments maybe required. The reprogramming decisions result in adjustments to individual control accounts. A reprogramming adjustment is represented as budget, cost, and schedule variances within an Over Target Baseline (OTB), or Over Target Schedule (OTS). Use the fields on the properties page of reprogramming adjustments to enter the total changes for a control account. The values appear on the CPR Format 1 report, in Section 8 - Columns 12a, 12b and 13.

Follow these steps:

  1. Open the control account.

    The properties page appears.

  2. Open the Control Accounts menu and click Reprogramming Adjustments.

    The reprogramming adjustments properties page appears.

  3. Complete the following fields:
    Cost Variance

    Defines the reprogramming adjustment cost variance aggregated from all costs recorded against control accounts at this level.

    Schedule Variance

    Defines the reprogramming adjustment schedule variance aggregated from all costs recorded against control accounts at this level.

    Budget

    Defines the reprogramming adjustment budget aggregated from all costs recorded against control accounts at this level.

  4. Save the changes.

More information:

Monitor Control Account Performance

Control Account Baselines

Contract Performance Report (CPR) Format 1 - WBS