Follow these steps:
The control accounts page appears.
The properties page appears.
Required. Defines the control account name.
Required. Defines the control account unique identifier.
Defines the control account description.
Required. Defines the organizational department, or subcontractor/ vendor group responsible for delivering the work within the control account. Select a unit from the same OBS structure as you selected for the contract. If you select a different unit, the baseline, and earned value metrics do not aggregate in the CPR reports.
Required. Defines the name of the control account manager (CAM). The resource is typically a member of the control account OBS unit.
Defines the name of the control account earned value analyst.
Defines the name of the control account financial analyst.
Defines the name of the control account scheduler.
Specifies the control account status.
Values: Rejected, Unapproved, or Approved
Default: Not selected
Defines the control account authorized budget (BAC). Manually enter the value. Use the field to monitor the progress of the authorized budget against the work package aggregated BAC. A variance can indicate the necessity for corrective action.
Read-only. Displays the aggregate BAC of all the control account work packages.
Defines the control account planned start date.
Defines the control account planned finish date.
|