Previous Topic: Create Lessons Learned ReportNext Topic: Create Product Filters


Track a Project Task as a Product

PRINCE2 Accelerator allows you to track the progress of a task as a product during the project life cycle. You can also create your own filter (product breakdown structure) to track the development of the task as a product. Creating a filter allows you to see all tasks flagged as products and then see the full product breakdown structure.

Since the flagged task is also displayed in a standard work breakdown structure, you can map this task (or product) to different tasks.

Follow these steps:

  1. Open your PRINCE2 project.
  2. Click Tasks.
  3. Click New.
  4. Enter the required information, and save.
  5. Select the Product check box to flag the task as a product, and save.