Previous Topic: Create Exception ReportNext Topic: Create Lessons Learned Report


Create End Stage Report

The PRINCE2 methodology involves dividing the project phases into discreet stages. At the end of each stage, the Project Board assesses the progress of the project to decide if they should proceed to the next stage.

The End Stage report provides progress update about a PRINCE2 project to the Project Board members using the following:

The Project Board uses this information to approve, ask for a revision, amend the scope, or stop the project.

Follow these steps:

  1. Open the PRINCE2 project.
  2. Open the Properties menu, and click End Stage Report.
  3. Select New.
  4. Provide the requested information and save the changes.