Set Multiple Baselines

When you maintain multiple baseline versions, the current version is the version from which earned value analysis (EVA) is measured. You can change the current version any time.

If you are using Open Workbench with CA Clarity PPM, you can set multiple baselines and can save the project back to CA Clarity PPM. By default, when you create a new baseline, it is selected as the current version. You can choose to select another baseline to be the current version.

When you create a new baseline, the name and code of the new baseline by default is baselineN, where N is an incremental number starting at 1. Double-click the cell to change the value.

Follow these steps:

  1. Open the Project ribbon.
  2. Click Manage in the Baselines group.
  3. Click New to add a new baseline to the grid. This baseline is selected as the current baseline version.
    Code

    Defines the code for the baseline.

    Name

    Defines the name of the baseline.

    Description

    Defines the description of the baseline.

  4. Click OK.