You can view a task's % Expended amount on the Advanced tab on the Task Properties dialog. Unlike % Complete, % Expended is a calculated field that represents the percentage of resource usage expended on a task. Because % Expended is calculated and can be more precise than % Complete, which is a user-defined value and is limited to 2 decimal places, earned value calculations such as BCWP may produce different results depending on which % Complete value you select.
|