The Dependencies tab on the Task Properties dialog displays dependency relationships for the selected task, including internal and external dependencies. You can use this tab to edit the dependency relationship and to add new dependency relationships.
Note: If you specify percent as the lag type and Finish-Finish as the constraint type, you are specifying the percentage of the successor's duration. If you specify percent for any other constraint type, you are specifying the percentage of the predecessor's duration.
Overlap Tasks
If you want two tasks to be scheduled on the same day because the resource has remaining availability on that day, enter -1.00 as the lag to overlap the tasks.
Zero Lag
To schedule two dependent tasks, schedule first on one day and the next on the following day, enter zero as the lag amount.
Follow these steps:
Specifies the task's dependency relationship.
Default: Successor
Options: Successor or Predecessor
Specifies the constraint type to be placed on the task's start or finish date.
Default: Finish-Start
Options: Start-Start, Start-Finish, Finish-Start, or Finish-Finish
Defines the number that represents the days or percent to indicate the amount or time between, or overlapping, the task start or finish dates.
Note: The constraint type used is the type you specify.
Specifies the lag type.
Default: Daily
Options: Daily or Percent
|