Vary Resource Billing Rates

You can vary a resource's billing rate to show more accurately the total cost a resource has on your project. For example, you may want to show a varying billing rate if a resource gets a pay raise mid-project. You can update a resource's billing rate using:

For Example:

Suppose that a resource's billing rate is based on the following rate matrices:

To vary a resource's billing rate, in a view that displays resource billing rate data, double-click the resource's Billing Rate cell and enter the new rate. To change the altered billing rates back to a single rate for a resource, open the General tab on the Resource Properties dialog and edit the rate.

Note: For more information, see the Project Management User Guide.

More information:

Manage CA Clarity PPM Projects using Open Workbench

Define a Resource's or Role's General Properties and Availability

Cost Rate and Currency Data