Override Task Lock during Autoschedule

You can override the lock on tasks while autoscheduling. For example, if you have a task that is locked between February 25, 2008 and April 4, 2008, autoschedule distributes the assignment's ETC to the task between the two dates. If you do not override the lock and autoschedule changes the task's end date to April 25, 2008, the assignment's ETC remains between February 25, 2008 and April 4, 2008. However, if you choose not to override the lock, the assignment's ETC is distributed between February 25, 2008 and April 25, 2008, per the assignment's loading pattern.

When scheduling locked tasks using this option, autoschedule adheres to the following rules:

Follow these steps:

  1. Open the Project ribbon.
  2. Click Autoschedule in the Schedule group.
  3. Select the Schedule Assignments on Locked Tasks check box, and click OK.

More information:

Define the Scheduling Constraints for the Task

Define Autoschedule Parameters

Lock Tasks in Place