Release Resources from Task Assignments
When you release a resource from a task assignment, the resource is still available for assignment to other tasks in the project.
Follow these steps:
- Right-click a task and click Modify in the shortcut menu.
- Open the Resources tab.
- Select the resource assignment you want to release in the Assigned Resource grid, and click Release.
- Click OK.
More information:
Define the Resources Properties
Define Resource Actual Usage on Tasks
Define Resource Estimate to Complete on Task
Define Resource Maximum Percentage on Tasks
Transfer Task Assignments between Resources