You can vary a resource's billing rate to show more accurately the total cost a resource has on your project. For example, you may want to show a varying billing rate if a resource gets a pay raise mid-project. You can update a resource's billing rate using:
You can save the changes that you make to the resource's billing rate to an Open Workbench .rmp project file but you cannot save these changes back to CA Clarity PPM.
For Example:
Suppose that a resource's billing rate is based on the following rate matrices:
To vary a resource's billing rate, in a view that displays resource billing rate data, double-click the resource's Billing Rate cell and enter the new rate. To change the altered billing rates back to a single rate for a resource, open the General tab on the Resource Properties dialog and edit the rate.
Note: For more information, see the Project Management User Guide.
|