Edit Subproject Access in Master Projects

Use the Subproject tab of the Project Properties dialog to change access to the subproject from read/write to read-only in a master project. When selected, any changes you make to the subproject from the master project are not saved when you close the master project.

Note: This tab only appears on the Project Properties dialog for subprojects that were inserted as an entire project into a master project.

Follow these steps:

  1. Open a view that displays the task detail pane.
  2. Right-click the subproject (proxy task) and click Modify in the shortcut menu.
  3. Open the Subproject tab.
  4. Clear the Read-only check box, and click OK.