Previous Topic: CalendarsNext Topic: Create New Calendars


Apply a Calendar to Projects

You can apply a calendar other than the default calendar to all of the projects you have open during an Open Workbench session. During an Open Workbench session, you can switch calendars as often as you want to create new scenarios for your projects.

Follow these steps:

  1. Open the Project ribbon.
  2. Click Edit in the Calendar group.
  3. Select the name of the calendar from the Current Calendar drop-down in the System Options section.

    The calendar applies to all of the projects you have open.

  4. Click OK.