Use the Defaults tab of the Options dialog to define the default project-scheduling behavior, such as the loading pattern, units, and the projects duration type. You can also define the default dependency options, such as the dependency type, lag, and lag type.
Follow these steps:
Defines the loading pattern that is used when assigning resources to tasks.
Values: Fixed, Contour, Front, or Back
Default: Front
Select to specify that the resource's duration type is fixed.
Specifies how the resource value is measured.
Values: Days or Hours
Default: Hours
Specifies whether the ETC is calculated automatically. If you select this check box, the ETC is calculated automatically for all resource assignments. You can view and manage these automatically calculated ETC values in CA Clarity PPM, also.
Note: CA Clarity PPM and Open Workbench use the same method for calculating ETC.
Default: Cleared
Defines the dependency type.
Values: Finish-Start, Start-Start, Finish-Finish, or Start-Finish
Default: Finish-Start
Defines the number of days (daily lag type) after the predecessor task's constraining date, or percent complete (percent lag type), that the successor task's constraining date begins.
Lag is the predetermined amount of time between the start and/or finish time of two tasks in a project plan.
Defines the lag type.
Options: Daily or Percent
Default: Daily
|