To shift or scale all or a portion of the resource allocations in one project, use the Shift Allocation option. This option is useful when you want to extend project allocations beyond the allowable time-scaled view, which extends only for six months by default. You can move resource allocations both back and forward in time.
For example, suppose that an allocation period starts on May 1. The period continues at its default rate of 100 percent through the end of May. The period then extends through June at the reduced allocation of 50 percent. You shift the allocation to start on June 1 and extend through July 2 (for 31 calendar days) at 100 percent. The period goes through August 2 at 50 percent. You can also shift allocations for time spans that contain no segments.
You cannot change the project schedule dates. Use these dates as guidelines on how far you can shift work back or forward. You cannot shift work before the start date, and you cannot shift work past the finish date.
Follow these steps:
Defines the start and finish dates of the project unless they have been changed. These dates create the period that can shift.
Defines the beginning date for the data being shifted.
Note: If you leave the field blank, no shifts occur.
Defines the last date for shifting allocations. Allocations cannot shift beyond the last date.
Defines the percentage change in the allocation that is required for the shift.
Note: If you leave the field empty, no scaling occurs.
|
Copyright © 2015 CA Technologies.
All rights reserved.
|
|