Define Work Shifts in Calendars

The default base calendar shows two 4-hour shifts with one hour for lunch for a total of eight work hours. You can set new shifts.

Follow these steps:

  1. Open Administration, and from Project Management, click Base Calendars.
  2. Click the name of the calendar.

    The edit calendar exceptions page appears.

  3. To modify only one resource calendar:
    1. Open Home, and from Resource Management, click Resources.
    2. Select a resource or role.
    3. Click the Calendar tab.
  4. Select the month at the top of the calendar.
  5. Select the check box next to the days having the same shift, and click Set Shifts.
  6. Enter the start and end times for up to four shifts.
  7. Save your changes.