Specify Staffing Requirements

Specify staffing requirements for a resource or role that is added to the project. When done, you can create requisitions for the staffing requirements.

Follow these steps:

  1. Open the project and click Team.
  2. Click the Properties icon for the resource or role for which you want to specify staffing requirements.
  3. Complete the requested information. The following fields require explanation:
    Requirement Name

    Defines the staffing requirement name. Each requisition can access all information from the team member. For example, skills, allocation needed, or role on which the requisition is based.

    Start Date

    Defines the date for the resource to start work on the project.

    Finish Date

    Defines the date for the resource to end work on the project.

    Default Allocation %

    Defines the percentage of time to allocate the resource to the project (you can enter 0 percent). If you change the amount in this field, the value replaces the value in the Default % Allocation field on the staff member properties page.

    Booking Status

    Defines the booking status for the resource.

    Values:

    • Soft. The resource is tentatively scheduled to work on the investment.
    • Hard. The resource is committed to work on the investment.
    • Mixed. The resource is both soft and hard allocated to the investment, or the soft allocation for the resource does not match the hard allocation.

    Default: Soft

    Request Status

    Defines the requisition status for a requisition that is linked to the team record. Whenever the actual requisition status changes on the requisition properties page, this request status field is updated. The requisition status provides the project manager an indicator of the state of their requisitions. When you first create a staffing requirement, the request status is "New". If more than one requisition is attached, then this field displays the status of the open (not closed) requisition. You can use this status for manually booking a resource without using a formal requisition.

    Investment Role

    The role of resources that are requested for the investment. For example, developer, business analyst, or architect.

    Staff OBS Unit

    Defines the staff member OBS Unit affiliation.

    Default: The project Staff OBS Unit value if one is defined for the project.

    Open for Time Entry

    Specifies if the resource can enter time against a specific project.

    Default: Selected

    Resume Keywords

    Defines the keywords in the resume of the resource.

    Planned Allocation

    Represents the duration that the resource is required on the project. The field represents the total availability of the resource for the project, as the project manager requests.

    Hard Allocation

    Represents the total hard-booked availability of the resource to the project, as the resource manager specifies. No hard allocation value exists until the resource manager hard-books the allocations.

  4. Save the changes.