If the project gets extended, you can add additional planned allocation for a resource.
The submit, propose, and accept process for a requisition is identical to the process described in the earlier sections. The two requisitions (created initially and the other for additional booking) are stored as two separate records of the individual transactions.
To un-book a resource, you reduce the planned booking. To request additional booking, you increase the planned booking compared to the hard-booking.
For an additional and unbook requisition, you can change allocations using the Shift Allocation option. Create a regular requisition and select the Unbook option to unbook a requisition. You require performing the two distinct actions as separate tasks. A team record can have up to one each of open and unbook requisitions at the same time.
Follow these steps:
The new requisition automatically asks for the difference between the planned and committed time.
|