Use the following procedure to enter the time-varying ETC segments for a resource assigned to a task. The time-varying ETC segments are displayed in the Usage column in the assignments list on the task properties page. Each time-varying ETC cell displays the work effort according to the work effort setting for the assignments list. The total ETC for the resource assignment is automatically calculated.
For fixed resource loading pattern, you can enter time-varying ETC in tentative-schedule and capacity planning scenario modes.
Follow these steps:
Defines the role for this resource on this task.
Defines the date to start the task assignment for a resource. The list pages or portlets display the start date.
Default: Task start date
Note: Define the assignment to start on or after the task start date. If an assignment has actuals, the field is read-only.
Defines the date to complete the task assignment for a resource. The list pages and portlets display this completion date.
Default: Task completion date
Note: Define the assignment to finish on or before the task completion date.
Note: The segments you define can extend beyond the task start or finish date depending on task date editing rules. When save your changes, the task start and finish dates change to reflect the new dates, and the project start or finish dates adjust accordingly.
Displays the estimate of remaining hours to complete the task. The estimate is based on the allocation percent for the team staff member between assignment start and finish dates. Also based on the number of hours the resource is available each day.
Specifies the loading pattern to distribute the ETC for a task assignment over the duration of the task. Autoschedule schedules the work based on this loading pattern.
Select Fixed to enter the distribution of the work effort.
|
Copyright © 2015 CA Technologies.
All rights reserved.
|
|