

Teams (projects and investments) › About Resource Allocation › Manage Resource Allocations › Generate Estimates Based on Resource Allocation
Generate Estimates Based on Resource Allocation
Use the following procedure to generate estimates based on allocation.
The Estimate from Allocation option is available only for resources that are assigned to effort tasks.
Follow these steps:
- Open the project and click Team.
- Select the check box next to the name of the resource, and from the Actions menu, click Estimate from Allocation.
The number in the ETC column refreshes to match the Allocation number.
Copyright © 2015 CA Technologies.
All rights reserved.
 
|
|