

Autoschedule › Publish Tentative Schedules
Publish Tentative Schedules
Publishing the tentative schedule replaces the plan of record (POR) with your tentative schedule and unlocks the project.
Follow these steps:
- Open the project and click Tasks.
- Open the Tasks menu and click Gantt.
The Gantt view appears.
- Click the down arrow for the Autoschedule With Options icon in the Gantt view, and click Publish Tentative Schedule.
- Click Yes to confirm.
Copyright © 2015 CA Technologies.
All rights reserved.
 
|
|