Previous Topic: Schedule a ServiceNext Topic: Enable Financial Transactions for a Service


Define a Budget for a Service

Use a simple budget to define the planned cost, net present value (NPV), return on investment (ROI), and breakeven information for the service. You can also define planned costs and benefits for a service.

When you set the start and end date for a budget, funding flows constantly and evenly over the period. A detailed financial plan lets you budget costs over multiple periods.

Note: Data from any detailed plans override the simple budget, and the fields on the page become read-only.

Finance managers set up defaults that define how financial plans can be created and the financial time periods used. The investment managers create multiple financial cost plans as estimates for a budget. They can submit the most appropriate cost plan for approval as a budget. Finance managers approve the submitted cost plans.

Follow these steps:

  1. Open the service.
  2. Open the Properties menu, and click Budget.
  3. Complete the following fields in the financial planning section:
    Currency

    Specifies the currency for calculating the budget and forecast values.

    Budget equals Planned Values

    Specifies if the budget values in the budget properties of an investment match the planned values. If a detailed budget plan exists for the investment, all the field values in the Budget section are display-only. The fields reflect the values in the detailed budget plan. When the check box is cleared, you can edit the budget fields.

    Default: Selected

    Calculate Financial Metrics

    Specifies if financial metrics for the investment are calculated automatically. If unselected, you can define the financial metrics manually.

    Default: Selected

  4. Complete the following fields in the financial metrics options section:
    Use System Rate for Total Cost of Capital

    Select the field to calculate the total cost of capital at system rate.

    System Rate

    Displays the system rate for calculating the total cost of capital.

    Investment Rate

    Displays the investment rate for calculating the total cost of capital.

    Initial Investment

    Defines the initial investment on the service.

    Use System Reinvestment Rate

    Select the field to calculate the total cost of capital at the system reinvestment rate.

    System Rate

    Displays the system rate for calculating the total cost of capital.

    Investment Rate

    Displays the investment rate for calculating the total cost of capital.

  5. Complete the following fields in the planned section:
    Planned Cost

    Defines the total planned cost for the investment. The value is distributed between the Planned Cost Start and the Planned Cost Finish dates.

    Planned Cost Start

    Defines the scheduled start date for the investment budget.

    Planned Cost Finish

    Defines the scheduled finish date for the investment budget.

    Planned Benefit

    Defines the anticipated financial benefit for the investment. The value is distributed between the planned benefit start and finish dates.

    Planned Benefit Start

    Defines the scheduled start date for the investment benefit.

    Planned Benefit Finish

    Defines the scheduled finish date for the investment benefit.

    Planned NPV

    Displays the planned net present value (NPV), which is calculated based on the following formula:

    Planned NPV = Planned Benefit - Planned Cost
    

    Note: To make this field available for data entry, clear the Calculate NPV Data field.

    Default: Locked

    Planned ROI

    The value in the field is calculated based on the following formula:

    Planned ROI = Planned NPV / Planned Cost
    

    Note: To make the field available for data entry, clear the Calculate NPV Data field.

    Default: Locked

    Planned Breakeven

    Displays the date and amount to indicate the period and value at which the program becomes profitable.

    Note: To make the field available for data entry, clear the Calculate NPV Data field.

    Default: Locked

    Planned IRR

    Displays the planned internal rate of return for the investment.

    Planned MIRR

    Displays the planned modified internal rate of return (MIRR) for the investment.

    Planned Payback Period

    Displays the date of the investment planned payback period.

  6. Complete the following fields in the Budget section:
    Budget Cost

    Displays the total budgeted cost for the investment

    Budget Cost Start

    Displays the budgeted cost start date of an investment.

    Budget Cost Finish

    Displays the budgeted cost finish date of an investment.

    Budget Benefit

    Displays the budgeted benefit for an investment.

    Budget Benefit Start

    Displays the budgeted benefit start date of an investment.

    Budget Benefit Finish

    Displays the budgeted benefit finish date of an investment.

    Budget NPV

    Displays the budgeted NPV (Net Present Value) of this investment.

    Budget ROI

    Displays the budgeted ROI (Return on Investment) of this investment.

    Budget Breakeven

    Displays the date when the investment budgeted cost equals the budgeted benefit.

    Budget IRR

    Displays the budgeted internal rate of return for the investment.

    Budget MIRR

    Displays the budgeted modified internal rate of return for this investment.

    Budget Payback Period

    Displays the date of the investment budgeted payback period.

  7. Save the changes.