Delete unnecessary line items and submit the cost plan as a replacement for the budget. For example, if you want to remove a line item from the budget plan, delete the line item in the cost plan. Submit the revised cost plan as a replacement for the budget plan.
Note: Select Replace to delete line items. Selecting Merge prevents the deletion and the line item remains in the submitted budget plan.
Example: Delete a Role and Replace the Budget
Several months before the project starts, Alice discovers that she must transfer the headcount of a test engineer to another project. She deletes the line item for the role for the junior test engineer from the cost plan, ProjectA_estimatedCP-00, and submits the plan for approval. Alice selects Replace to remove the line item from the budget.
Follow these steps:
Note: If the cost plan is already the plan of record, skip this step.
Note: If you receive the following message, another cost plan for the investment exists as a submitted budget plan.
Error:A submitted budget already exists.
The submitted budget plan must be approved or rejected before you can submit another plan for approval.
You have submitted a cost plan for approval that replaces the existing budget.
|