To start capacity and portfolio planning, staff your most promising ideas with resources. Ideas are not associated with tasks and staffing them does not result in long-term commitments for that staff. For example, you can staff an idea with team members to perform up-front work before approving the idea. Add additional staff to estimate and plan capacity before converting the idea into a project, investment, or service.
You can allocate roles or resources, and labor or non-labor types. The staff can record the time that they spent working on an idea on their timesheet.
Use a role as a placeholder when you do not know the name of the resource you want to staff on your idea. When a specific resource is not available, you can staff your idea with multiple instances of a role. For example, assign programmer (1) and programmer (2) to represent two different requirements with a programming role.
Note: You cannot staff multiple instances of the same named resource to an idea.
Follow these steps:
The Select Resources page appears.
Use the Search Filter to find resources or roles by name or other criteria.
Displays the role of the resource, which can be different from the primary role selected in the resource profile.
Displays a yellow checkmark if the resource or role is allowed to enter time for the idea.
Displays the resource or role booking status:
Displays the team member allocation start date. If not defined, the date defaults to the start date of the idea.
Displays the team member allocation finish date. If not defined, the date defaults to the finish date of the idea.
Displays the team member percent allocation to the idea. Each staff member is assigned to the idea at 100 percent of the resource available time by default.
Displays the number of hours the resource has been tentatively booked to the idea. Unless you change the booking dates, staff members are automatically booked for the entire duration of the idea. This field cannot be edited. Its value changes to reflect edits that you make using the following options:
Displays the total number of hours the resource has recorded to date on this idea.
Displays the time posted to incidents associated with this idea.
Displays the aggregated total actual time posted. This value is the sum of the allocated actuals and the incident actuals.
Note: When adding resources to your idea staff, you could easily over-allocate the resource by mistake. In this case, a confirmation page appears. The available hours for a resource can be less than the total number of requested hours. In this case, instead of the Booking Confirmation page, the Remaining Availability Confirmation page appears.
Over-allocates the resource.
Books the resource for the amount listed in the Remaining Availability column.
Note: Staff allocation is the period during which a resource is booked to an idea. Unless you change the booking dates, staff members are automatically booked for the entire duration of the idea. The allocation amount granted for a resource can be calculated as follows:
Total number of working days * Number of available hours per day
The total working days includes start and finish dates. ETC is based on the number of hours a resource is assigned to the idea.
|