Remove Resource Actual Usage on Tasks
Use the following procedure to remove actuals for a specific resource that is assigned to a task. You can also use this procedure if you are using Open Workbench with CA Clarity PPM and if the resource's track mode, the method of time capture, is set to none in CA Clarity PPM.
Note: For more information, see the Resource Management User Guide.
You can remove actuals or you can convert any actual usage that has been recorded after the date back to ETC usage.
Follow these steps:
- Right-click a task in the view and click Assignments.
- Complete one of the following steps in the Assigned Resources grid:
- Clear the Act Thru date to remove all actuals.
- Change the Act Thru date to an earlier date to convert any actual usage that has been recorded after the date back to ETC usage.
- Click OK.