You can autoschedule projects from a finish date to help you find out on which date your project has to start in order to meet a required finish date. When you schedule your project based on its finish date, autoschedule performs three traversals of the project. In the second and third traversals, it goes over the tasks backward first and enforces finish constraints over start constraints so that the project is scheduled to start as late as possible.
When you run autoschedule using a project's finish date, it does the following:
Follow these steps:
The Start Date field toggles to the Finish Date field. The current project finish date displays in the Finish Date field.
|