Display Baseline Data in Views

You can display one baseline in a view at a time. To view baseline information, first include the fields that display baseline data in one of your views. You can display the current baseline in a spreadsheet view, such as the Gantt Chart view, against the current status of the project. Special baseline markers on Gantt bars indicate the baseline information to differentiate the baseline information from the current schedule.

The following procedure explains how to include the fields that display baseline data in a view.

Follow these steps:

  1. Open a view that displays the task detail pane.
  2. Add the following fields:
  3. Add the Resource Baseline Cost field in the resource detail pane.

The following procedure explains how to display a baseline.

Follow these steps:

  1. Double-click the Gantt chart.
  2. Select the Baseline check box in the Gantt Bars group and click OK.

More information:

Baseline Projects