Previous Topic: Accept Pending EstimatesNext Topic: Schedule Projects


Reject Pending Estimates

Use the Pending Estimates dialog to reject the pending estimates for the entire project, for the tasks that are displayed in a view, or for selected tasks. When you reject pending estimates, Open Workbench removes the pending estimates and the pending actuals amounts. The resource's pending ETC remains the same.

Follow these steps:

  1. To reject pending estimates for selected tasks only, open the project and select the tasks you want to reject estimates for. Otherwise start with step 2.
  2. Open the Project ribbon.
  3. Click Pending Estimates in the Schedule group.

    Note: This selection is disabled if you are viewing a read-only copy of a project or if there are no pending estimates. Pending estimates are updated only if you have saved changes to the current pending estimates.

  4. Define the scope for pending estimates by selecting project, view, or selected tasks, and select Reject Pending Estimates.
  5. Click OK.

More information:

How to Enter Pending Estimates

Accept Pending Estimates

Display Pending Estimates Data in Views