Use the Pending Estimates dialog to reject the pending estimates for the entire project, for the tasks that are displayed in a view, or for selected tasks. When you reject pending estimates, Open Workbench removes the pending estimates and the pending actuals amounts. The resource's pending ETC remains the same.
Follow these steps:
Note: This selection is disabled if you are viewing a read-only copy of a project or if there are no pending estimates. Pending estimates are updated only if you have saved changes to the current pending estimates.
|