Project Tasks › How to Track Resources › Track Resources by Total Actual Usage
Track Resources by Total Actual Usage
You can record periodic actual usage using the Resources tab on the Task Properties dialog or by editing a view that displays the Actual field name.
Follow these steps:
- Open a view that displays the task detail pane.
- Select a task and click in the cell displaying total actual usage.
- Enter the total actual usage for each applicable cell on the timescale.