Define the Advanced Properties

Use the Advanced tab on the Task Properties dialog to define a task's advanced management details, such as defining, removing, or editing task scheduling constraints. The Advanced tab provides a central location from where you can set or change task-related values. All of the task's attributes display on this tab.

This tab displays a Fields grid that contains the following columns:

Note: The fields that are available for editing depend on your access rights. If a field is not available for selecting or editing, it is disabled (by default).

Follow these steps:

  1. Open a view that displays the task detail pane.
  2. Right-click a task and click Modify in the shortcut menu.
  3. Open the Advanced tab.
  4. Enter the values in the Value column for the following fields in the Fields grid:

    Note: The value you can enter depends on the field you have selected.

    % Complete

    Enter a value between 0 and 99 to identify the percentage of work that has been completed for a task. When the tasks are 100% complete, Open Workbench automatically inserts 100 into this field.

    Actual % Spent

    Indicates the completeness of a task out of 100%.

    ACWP

    Defines the actual cost of the work performed, which is the cost of the completed portion of assignments to a task based on the actual usage.

    AV

    Defines the difference between the Budgeted Cost of Work Scheduled (BCWS) and the Actual Cost of Work Performed (ACWP).

    BAC

    Defines the budget at completion, which is the budgeted cost of resource usage for the baseline plan.

    Baseline Fixed Duration?

    Defines whether the baseline is set for a fixed duration.

    BCWP

    Defines the budget cost of work performed. BCWP is the cost of the completed portion of a task based on baseline total usage. BCWP is also an earned value calculation.

    BCWS

    Defines the budget cost of work scheduled, which is the cost of baseline total usage through the Project As-of date.

    Category

    Defines the name of the group or class to which this task belongs.

    EAC

    Defines the estimate at completion, which totals the cost incurred to date and the expected costs for incomplete tasks to give a projected figure.

    Unplanned

    Defines whether the task is unplanned.

  5. Click OK.

More information:

Update the Task Properties

Define the Scheduling Constraints for the Task

Lock Tasks in Place

View Task Percent Expended Amount