Use the update earned value totals - contracts job to track contract progress by calculating earned value. This job calculates the current earned value data totals through the current date for a contract or set of contracts based on the parameters you select. The data is stored in a reserved row in the PRJ_EV_HISTORY (earned value history) table. The saved current earned value data totals are displayed in fields on contracts.
You can schedule this job to run in the background. You can invoke this job on demand from within the contract by updating the contract earned value.
To calculate current earned value, the contract requires a current baseline.
This job cannot run concurrently with any other instance of the update earned value totals - contracts job.
The following parameters are provided:
Note: If you do not complete any of the parameters, all contracts are processed.
Defines the name of the contract.
Defines the name of the OBS Unit.
Defines the name of the contract manager.
|